COLLECTION SYSTEM EVALUATION PROGRAM
COLLECTION SYSTEM EVALUATION PROGRAM
Continue implementation of and complete a 5-year system wide plan to evaluate the entire sanitary sewer collection system (300 miles of lines with 75 miles completed) and develop schedule for repairs.
The evaluation will include the inspection of all manholes and collection system lines using smoke testing first to be followed by Closed Circuit Television (CCTV) Inspections of high priority areas.
The evaluation will be utilized to prioritize and schedule major point repairs and also to plan and prioritize major rehabilitation projects for the future.
A schedule to complete major rehabilitation projects identified during the evaluation will be submitted for EPD approval by December, 2018.