MANHOLE REPLACEMENT/REHABILITATION PROGRAM
MANHOLE REPLACEMENT/REHABILITATION PROGRAM
Continue existing program completing inspection of approximately 3,390 remaining manholes (2,610 inspected to date) and prioritizing replacement or rehabilitation of the most deteriorated manholes. Complete the replacement or rehabilitation of a minimum of 60 manholes each year until all priority 1 manholes are completed. A schedule will be submitted to EPD for ongoing rehabilitation to address priority 2 and all remaining manholes on an annual basis.
LIFT STATION REHABILITATION/REPLACEMENT PROGRAM
Continue with existing rehabilitation/replacement program until all existing older lift stations are completed. This will include connection to SCADA and/or auto-dialer systems along with emergency power capabilities for connection to portable generators should power to station be lost.
PURCHASE PORTABLE GENERATORS FOR LIFT STATIONS
The purchase of three portable generators will be completed (1per year) so that any existing lift station, not wired with two independent electric feeds, can be quickly connected to a portable generator for emergency power needs. In addition to the generators, the city has worked with Godwin Pumps to meet emergency bypass pumping needs at each of our lift stations whenever needed.