PUMP STATION, FORCE MAIN, HEADWORKS AND
PUMP STATION, FORCE MAIN, HEADWORKS AND
EQUALIZATION BASIN PROJECT
Design and construct two new master pump stations and two smaller pump stations along with a new force main to a new headworks structure with grit removal and bar screens at the same location for the new Withlacoochee WPCP. In addition a 6.0 MG equalization basin will be included at this site for initial wet weather flows and future flow equalization through the new Treatment Plant. The flow from this project will be gravity fed to the existing WPCP for final treatment and discharge utilizing the existing plant outfall. This project will replace an existing 54-inch gravity sewer main to the current plant as well as the existing influent pump station, both of which are highly prone to severe inflow and flooding from the Withlacoochee River.
Design of Three Construction Packages to be bid simultaneously:
- Pump Stations – Major Stations at Gornto Road and Remer Lane with Two Minor Pump Stations at Valdosta State Prison and Trailer Park on 133
- Forcemains – 6 miles of 30” and 42”
- Headworks and Equalization Tank
Project removes over 50% of sewer flow from Meadowbrook Sewer Trunk Line.