Solar Dublin High School groundbreaking tomorrow

Dublin gets the jump on the rest of Georgia again: Dublin High School will get a megawatt of solar electricity through a lease agreement with a private company using local government bonds to get around Georgia’s special financing problem.

Kenny Burgamy reported for for 13wmaz.com Thursday, Solar Plant To Be Located at Dublin High,

Dublin High School of Dublin City Schools will soon implement 1 megawatt of solar energy.

The 4,000 panel solar power plant will be the largest in Central Georgia and is expected to save the school 40 percent in energy costs.

Dublin City Schools Superintendent Chuck Ledbetter told 13WMAZ, “The facility will be built and owned by private business and the school system will lease the solar power plant, saving us money in energy costs.”

The original plan was developed more than 15-months ago by German based MAGE SOLAR, which has a plant located in Laurens County.

The story has been carried by GPB by Athens Banner-Herald via AP.

This installation is similar to but slightly different from Continue reading

Fukushima still broken 2 years after

Tomorrow is the second anniversary of the earthquake and tsunami that heavily damaged four of the six nuclear reactors at Fukushima Dai-ichi in Japan on 11 March 2011, also known as 3/11. The broken reactors at Fukushima continue to leak radioactive substances into groundwater, the sea, and the air, where it is carried across oceans to the U.S. and elsewhere. And it could still get much worse: if the No. 4 reactor pool, still suspended in the air, collapses and causes the disintegration of spent fuel rods from all the other reactors there, Tokyo, 200 miles away, will have to be evacuated. Fukushima’s GE reactors are the same GE Mark I design as Southern Company’s Plant Hatch 1 and 2 only 100 miles from here at Baxley, GA, and about 200 miles from Atlanta and Charleston. Hatch is leaking radioactive tritium into our groundwater again. Five more reactors within 500 miles of here are also GE Mark I.

Among the 311 or so facebook pages and websites about Fukushima or against nuclear power is this concise one, Unplug Nuclear Power, which offers a simple action anyone can take tomorrow:

On 3/11, we will mark Fukushima day by using as little utility supplied electricity as possible. This direct Action is designed to punish the utility companies for continuing to push for nuclear power even after the Fukushima disaster has proven that it is just too dangerous. On that day, we will punish them in the only way that they understand, by denying them our money. There will be four levels of participation, go to the website, www.unplugnuclearpower.com for a more complete description. Also, be sure to join the Event. Finally, if you are in a group our organization that can endorse this Action, please let us know.

As Jeremy Rifkin so concisely spelled out, nuclear power is over Continue reading

Scorecard on Internet and Energy at the Bird Supper

Gretchen Quarterman, Dexter Sharper, Bill Slaughter, and others at the Bird Supper in Atlanta

On the 27th of February I posted Internet and Energy at the Bird Supper and Gretchen and I went to the Bird Supper in Atlanta and discussed those four bills with legislators. Our local elected officials were lobbying on the same side of many of the same bills. It’s past crossover day now, when bills are supposed to be approved by one house of the Georgia legislature in order to be taken up by the other. How did that come out? We all beat the mighty telcos and cablecos on two bills! But Georgia Power is even mightier, and won on two bills. Plus one legislator’s name is connected with 3 out of 4 of those bills. And our local delegation cancelled itself out on the one vote that actually went to the floor.

Internet Access: help stop two telecommunications bills

The local Industrial Authority, Chamber of Commerce, Valdosta City Council, and Lowndes County Commission have recently realized that fast Internet access is essential to attract businesses, for their employees to work at home, for applicants to apply for jobs, for students to submit assignments, and for general quality of life. And there’s good news from the legislature!

Continue reading

SC Edison knew San Onofre nuke steam generators were flawed before installation

Southern California Edison knew the new steam generators were defective years before then even installed them in the San Onofre nuclear reactors, acccording to a report just released. These are the generators that failed and caused both San Onofre reactors to shut down. SD Edison wants to restart one of them, and this document came out in that process. Southern Company would never do this, right? We shouldn’t worry about failed concrete or 15, no now 19, months delay while the Georgia legislature won’t even limit charges to Georgia Power customers for cost overruns. Nope, no worries.

Friends of the Earth PR 8 March 2013, San Onofre: Secret Report Confirms Edison Knew of Major Problems; Friends of the Earth: ‘Bombshell’ for plans to restart crippled reactor

WASHINGTON—March 8—A secret Mitsubishi Heavy Industries report released today confirms that Southern California Edison knew about serious problems in the radically redesigned replacement steam generators for the San Onofre nuclear reactors years before the defective equipment was installed, yet failed to make changes to fix the problems. The report was released today by the Nuclear Regulatory Commission after Senator Barbara Boxer (D-Calif.) and Representative Edward Markey (D-Mass.) revealed its existence and demanded it be made public.

The report documents that Edison knew

Continue reading

Already: Solar grid parity without subsidies in India and Italy

Solar power is going so well worldwide that Deutsche Bank has just increased its projections for global demand, noting that India and Italy have already in 2013 reached grid parity without subsidies with other sources of energy, and it expects the rest of the world to follow as early as 2014. The big winner is rooftop solar. Is Georgia paying attention?

Becky Beetz wrote for Global PV 26 February 2013, Deutsche Bank: Sustainable solar market expected in 2014,

Buoyed by bullish demand forecasts, and increasing utilization rates and pricing, Deutsche Bank forecasts a solar market transition from subsidized to sustainable in 2014. Italy REC solar photovoltaic plant

The German bank has raised its 2013 global solar demand forecast to 30 GW — representing a 20% year-on-year increase — on the back of suggestions of strong demand in markets including India, the U.S., China (around 7 to 10 GW), the U.K. (around 1 to 2 GW), Germany and Italy (around 2 GW).

Rooftop installations are, in particular, expected to be a main focus, says Deutsche Bank. A trend for projects being planned with either “minimal/no incentives” has also been observed, despite the belief that solar policy outlooks are improving, particularly in the U.S., China and India, and “other emerging markets”.

More analysis by Jeff Spross in ThinkProgress 3 March 2013, Solar Report Stunner: Unsubsidized ‘Grid Parity Has Been Reached In India’, Italy–With More Countries Coming in 2014.

As Renew Economy also points out, this is the third report in the past month

Continue reading

Levy Co. FL nuke likely not to be built

Cost already sunk Kewaunee, Calvert Cliffs, Crystal River, and are gnawing away at San Onofre: now it looks like new owner Duke is not likely to build Progress Energy's Levy County, Florida reactor. All that plus even in Georgia, even against all-powerful Georgia Power, there's a reaction against the cost of the always-later always-more-expensive new nukes at Plant Vogtle on the Savannah River. A reaction that's getting written up in the Valdosta Daily Times.

In the VDT today from AP, Some leaders souring on nuclear power costs. I'm quoting from the abcNews version because it includes the author's name, Ray Henry, and the original date, 3 March 2013. I added all the links and images.

As the cost of building a new nuclear plant soars, there are signs of buyer's remorse.

The second-guessing from officials in Georgia and Florida is a sign that maybe the nation is not quite ready for a nuclear renaissance. On top of construction costs running much higher than expected, the price of natural gas has plummeted, making it tough for nuclear plants to compete in the energy market.

In Georgia last week, Southern Co. told regulators it needed to raise its construction budget for Plant Vogtle in eastern Georgia by $737 million to $6.85 billion. At about the same time, a Georgia lawmaker sought to penalize the company for going over budget, announcing a proposal to cut into Southern Co.'s profits by trimming some of the money its subsidiary Georgia Power makes.

And Southern Company and Georgia Power slipped the Plant Vogtle schedule still more, from 15 to 19 months late.

The legislation has a coalition of tea party, conservative and consumer advocacy groups behind it, but faces a tough sale in the Republican-controlled General Assembly. GOP Rep. Jeff Chapman found just a single co-sponsor, Democratic Rep. Karla Drenner.

That's HB 267: Financing costs; construction of nuclear generating plant. And AP failed to mention Georgia Sierra Club's support for HB 267.

As a regulated monopoly, Georgia Power currently earns about 11 percent in profits when it invests its own money into power projects. Chapman's legislation would reduce those profits if the nuclear project is over budget, as is the current projection.

In Florida, there's a move to completely eliminate Construction Work in Progress (CWIP) such as is being used in Georgia to pre-fund the new Plant Vogtle nukes.

In Florida, lawmakers want to end the practice of utilities collecting fees from customers before any electricity is produced.

Florida only recently got CWIP, but Progress Energy has been quick to profit by it:

Continue reading

HB 267 Would Limit Georgia Power’s Profits on Vogtle’s Cost Overruns —GA Sierra Club

There’s still time to contact your state legislators about stopping Georgia Power profitting from cost overruns on the new nukes at Plant Vogtle. Georgia Sierra Club spells out why.

Georgia Power’s expansion at Plant Vogtle will bring us power that is dangerous, expensive and unnecessary.

You may remember a controversial bill the Georgia Legislature approved in 2009, SB 31, the Nuclear Construction Work in Progress (CWIP) bill, which forces Georgia Power ratepayers to pay the financing costs during construction, rather than over the life of the plant. Large users of electricity are exempt from the charge, but residential and mom and pop businesses have been paying for two years.

Even after that sweetheart deal, the Public Service Commissioners scrapped their staff proposal to stop the company from profiting on cost overruns for the project after they top $300 million.

The most recent reports from the independent monitor established by the PSC says

that the project is months behind and as of December, $88 million over budget. Georgia Power gets to earn 11.15% return on all expenses approved by the PSC, so the more they have to spend, the more they get to make and the more ratepayers get to pay!

Putting the profit issue aside for the moment, if the Georgia PSC ever decided to disapprove cost overruns, Georgia Power could take a page from the Mississippi Power playbook and just get the Legislature to let them issue bonds to pay for the work.

HB 267 by freshman Rep. Jeff Chapman excludes the collection of any profits on cost overruns beyond the $6.4 billion the Public Service Commission has approved. The bill is co-sponsored by Avondale Estates Democrat Karla Drenner, who is a member of the Utilities Committee, to which the bill was assigned. Passage of this bill would provide an incentive for Georgia Power to keep expenses down at Vogtle, something that SB 31 failed to do.

It isn’t fair for Georgia Power to profit to the tune of over 11% on delays, overruns and mismanagement, so ask your State Representative to support HB 267.

-jsq

China regains lead in solar and wind investment —Financial Times

Pilita Clark wrote for Financial Times 14 January 2013, China retakes renewables investment lead,

China has surged ahead of the US to regain its title as the world's biggest investor in renewable energy, new figures showed on Monday.

The article continues by trying to downplay solar and wind because of a drop in investment from other countries, while not mentioning that solar and wind deployments continue to climb. According to Todd Woddy in Forbes 22 January 2013, Chinese Solar Market Boomed In Q4, Accounting For Third Of Global Demand. China has incentive and is doing something about it, as Feifei Shen and Reed Landberg wrote for Bloomberg News 30 January 2013, China to Boost Solar Power Goal 67% as Smog Envelops Beijing.

How much are the Chinese investing? The FT story continues:

Continue reading

From 15 to 19 months late: Plant Vogtle nukes

Surprise! The already-billing but not-built new nukes at Plant Vogtle are going to be even later and cost even more. In December they were to be 15 months late; now it’s 19 months late, and the cost overrun expected is $740 million. History is repeating itself from the last time Southern Company and Georgia Power built nukes on the Savannah River. How about we pass HB 267 to stop Georgia Power from charging that cost overrun to customers?

Kristi Swartz wrote for the AJC yesterday, Vogtle nuclear project to take longer, cost more,

Georgia Power’s Plant Vogtle nuclear expansion project will take about 19 months longer to complete than originally expected and cost about $740 million more than originally thought, the company said Thursday.

Joseph A. “Buzz” Miller, Executive Vice President – Nuclear Development Southern Nuclear Operating Company Georgia Power said its share of the estimated $14 billion project will rise to $6.85 billion, up from $6.11 billion, because of increased capital costs and additional financing costs. Customers, who have been paying the financing costs since 2011, now will pay them for a longer period of time.

And the amount Georgia Power customers have to pay for Construction Work in Progress (CWIP) keeps ratchetting up:

Continue reading

Internet and Energy at the Bird Supper

Dear Bird Supper attendees,

Two things could greatly help south Georgia: better Internet access and solar power. You could help stop two telecommunications bills and help pass two energy bills for jobs and education in south Georgia.

Internet Access: help stop two telecommunications bills

The local Industrial Authority, Chamber of Commerce, Valdosta City Council, and Lowndes County Commission have recently realized that fast Internet access is essential to attract businesses, for their employees to work at home, for applicants to apply for jobs, for students to submit assignments, and for general quality of life.

  • HB 282 against muni broadband
    This bill would prohibit local governments from providing Internet access if any local census block has 1.5Mbps access. Localities may or may not want to do it themselves, but they shouldn't be prohibited from using this option now that it is obvious to everyone that the commercial incumbents are not doing the job. Legislators please vote this bill down.
  • HB 176 for higher cell towers with less local government oversight
    This really bad bill would let cell telephone companies build towers wherever they want to at any height, taking away local government power to regulate that. It could even let private companies exercise eminent domain. Legislators please vote this bill down.

Energy: help pass two energy bills

Solar power can be a distributed source of jobs in south Georgia. Antique laws and a subsidized nuclear boondoggle are hobbling solar power.
  • GA SB 51, The Georgia Cogeneration and Distributed Generation Act
    Senator Buddy Carter has introduced a Senate bill for the current session of the legislature, SB 51, "The Georgia Cogeneration and Distributed Generation Act of 2001". It attempts to fix Georgia's special solar financing problem, the antique 1973 Territorial Electric Service Act, which says you can only sell power you generate to your one and only pre-determined electric utility, at whatever rate that utility sets.
  • HB 267 Financing costs; construction of nuclear generating plant
    Stop Georgia Power from charging customers for cost overruns for Plant Vogtle, already 15 months behind schedule and a billion dollars overbudget for power that nobody has received, yet Georgia Power has already billed customers about $1.7 billion. Bipartisan cosponsors are Jeff Chapman (R—Brunswick) District 167 and Karla Drenner (D—Avondale Estates) District 85. This boondoggle on the Savannah River is what Georgia Power and Southern Company are doing instead of deploying solar inland and wind off the coast.

-jsq