BUDGET IMPACT: $3,369,213.71 GA-EPD has approved up to 3 mgd from 2 mgd. Four bids. Low bid Southeast Connections, LLC, from Conyers, GA.

Sprayfield Expansion Phase
Packet: ULDC text amendments, Loch Winn LTD rezoning, adoption of millage rates, USGS stream gauges, sprayfield expansion, watermain interconnection @ LCC
14 October 2024
 
BUDGET IMPACT: $3,369,213.71 GA-EPD has approved up to 3 mgd from 2 mgd. Four bids. Low bid Southeast Connections, LLC, from Conyers, GA.