Sabal Trail natural gas pipeline letters to Lowndes County

No letters from Lowndes County back to Sabal Trail were included in the open records response of last week, so should we conclude the county has not authorized surveys on any of its properties? The request to Lowndes County was for correspondence with Sabal Trail Transmission LLC about the proposed natural gas pipeline from Anniston, Alabama to Orlando, Florida, and the response included survey authorization forms for a list of parcels owned by Lowndes County, plus assorted descriptions and maps with very little detail. Sabal Trail still didn’t have a contract with Florida Power and Light, yet expected:

“Field survey work is scheduled to begin in September 2013.”

It looks like Sabal Trail sent letters about a bunch of parcels and then more about another one later. First they sent an introduction 19 June 2013 listing parcels 0146A-074-A, 0171 178, 0172 119, 0204 001, including a map. This appears to be the same map we’ve seen before posted by various news media:

[Map: 36" Greenfield Pipeline Approx. 465 Miles]
Map: 36" Greenfield Pipeline Approx. 465 Miles

Then they sent a letter 22 June 2013 with a survey authorization form for the same parcels. Then they sent separate letters 25 June 2013 for parcels 0146A-074-A, 0171 178, and 0172 119, 0204 001.

Also on 25 June 2013 Lowndes County Chairman Bill Slaughter informed us:

Lowndes County does not benefit from this proposal and has no responsibility for the approval other than that of a property owner potentially impacted by the proposed route as any other property owner in Lowndes County would be.

Apparently Sabal Trail thought of another one, because a few weeks later they sent a cover letter 15 July 2013 for Parcels 0098 003, 0098 004 with a slightly more detailed map, followed a few days later by a survey authorization form 19 July 2013.

[Map of Options A and B]
Map of Options A and B

Scans of all these letters are on the LAKE website.

-jsq

Lowndes County takes no responsibility for the pipeline –Bill Slaughter @ LCC 2013-06-25

You’re on your own if that pipeline company wants your property; the county government chooses to stay completely out of it, so said Lowndes County Chairman Bill Slaughter at the 25 June Regular Session of the Lowndes County Commission.

He read a prepared statement about a proposed natural gas pipeline. Why the county couldn’t put it on their website as a press release is mysterious. I’ve added the links:

Lowndes County has been contacted by representatives of McKenna, Long, Aldridge law firm of Atlanta regarding a proposed project expected to impact property owners of Lowndes County. Spectra Energy Company and its subsidiary, Sabal Trail Transmissions LLC anticipates construction of a 465 mile interstate natural gas pipeline from Anniston, Alabama extending through Georgia and coming through Lowndes County, terminating in Orlando, Florida.

This project is for the benefit of and is the responsibility of Florida Power and Light. Lowndes County has been Continue reading