New nukes make no financial sense –financial expert to GA PSC

If new nukes make no sense because of natural gas prices, they make even less sense with continually-dropping solar power prices.

Ray Henry wrote for AP yesterday, Regulator: New nuke plant now wouldn’t make sense,

If Georgia was starting from scratch, it would not build a nuclear power plant….

An analyst working for state regulators, Philip Hayet, said in written testimony that the total costs of building two more nuclear reactors at Plant Vogtle (VOH’-gohl) is more expensive than the next-best option, constructing natural gas plants.

Still, Hayet said it is cheaper in most scenarios to finish the nuclear plant rather than halt the project and instead build natural gas plants.

But it’s not cheaper to finish a nuke than to halt it and get on with wind offshore and distributed solar power throughout Georgia.

GA PSC didn’t publish Hayet’s calculations, using the old excuse of “they involve proprietary financial information from Southern Co. subsidiary Georgia Power”. But Edison Electric Institute didn’t need any proprietary financial information to compute that Continue reading

Telecommunications rules and rates @ GA PSC 2013-06-18

Telecommunications rules and rates were deferred and scheduled at the Georgia Public Service Commission meeting Tuesday 18 June 2013.

First item on the regular agenda was Docket # 35537

Title: Notice of Proposed Rulemaking to Promulgate Rules Governing Eligible Telecommunications Carriers 515-12-1-.35

There was lengthy discussion about the database provision and the $5 minimum charge in those rules. Commissioner Wise didn’t like the database as proposed and asked for an indefinite hold until they had a database that was verifiable.

Commissioner Echols asked whether the current proposal would be like a hold anyway, since it would involve another hearing. Staff said yes. Commissioner Everett asked Continue reading

Utilities levy an absurd tax upon the rest of their fellow-citizens –Adam Smith

What’s next door to Georgia Power, also a Southern Company, and raising rates on customers who are using less electricity? Alabama Power.

Rebecca Smith wrote for WSJ 21 March 2013, Return Rates for Utilities Get Harder Look

Households getting electricity from Alabama Power Co. are using 6% less than five years ago. But their monthly power bills still have increased by an average of 8%, partly because of a lucrative rate agreement that the utility brokered with state regulators 30 years ago.

“an absurd tax upon the rest of their fellow-citizens”
—Adam Smith

The deal allows Alabama Power, the state’s largest electric utility, to adjust its rates annually to maintain a return on equity, a measure of profit, of 13% to 14.5%. Now it is coming under fire from consumer advocates and one state utility commissioner, who argue that the utility’s profit levels are too high.

Continue reading

Already: Solar grid parity without subsidies in India and Italy

Solar power is going so well worldwide that Deutsche Bank has just increased its projections for global demand, noting that India and Italy have already in 2013 reached grid parity without subsidies with other sources of energy, and it expects the rest of the world to follow as early as 2014. The big winner is rooftop solar. Is Georgia paying attention?

Becky Beetz wrote for Global PV 26 February 2013, Deutsche Bank: Sustainable solar market expected in 2014,

Buoyed by bullish demand forecasts, and increasing utilization rates and pricing, Deutsche Bank forecasts a solar market transition from subsidized to sustainable in 2014. Italy REC solar photovoltaic plant

The German bank has raised its 2013 global solar demand forecast to 30 GW — representing a 20% year-on-year increase — on the back of suggestions of strong demand in markets including India, the U.S., China (around 7 to 10 GW), the U.K. (around 1 to 2 GW), Germany and Italy (around 2 GW).

Rooftop installations are, in particular, expected to be a main focus, says Deutsche Bank. A trend for projects being planned with either “minimal/no incentives” has also been observed, despite the belief that solar policy outlooks are improving, particularly in the U.S., China and India, and “other emerging markets”.

More analysis by Jeff Spross in ThinkProgress 3 March 2013, Solar Report Stunner: Unsubsidized ‘Grid Parity Has Been Reached In India’, Italy–With More Countries Coming in 2014.

As Renew Economy also points out, this is the third report in the past month

Continue reading

Levy Co. FL nuke likely not to be built

Cost already sunk Kewaunee, Calvert Cliffs, Crystal River, and are gnawing away at San Onofre: now it looks like new owner Duke is not likely to build Progress Energy's Levy County, Florida reactor. All that plus even in Georgia, even against all-powerful Georgia Power, there's a reaction against the cost of the always-later always-more-expensive new nukes at Plant Vogtle on the Savannah River. A reaction that's getting written up in the Valdosta Daily Times.

In the VDT today from AP, Some leaders souring on nuclear power costs. I'm quoting from the abcNews version because it includes the author's name, Ray Henry, and the original date, 3 March 2013. I added all the links and images.

As the cost of building a new nuclear plant soars, there are signs of buyer's remorse.

The second-guessing from officials in Georgia and Florida is a sign that maybe the nation is not quite ready for a nuclear renaissance. On top of construction costs running much higher than expected, the price of natural gas has plummeted, making it tough for nuclear plants to compete in the energy market.

In Georgia last week, Southern Co. told regulators it needed to raise its construction budget for Plant Vogtle in eastern Georgia by $737 million to $6.85 billion. At about the same time, a Georgia lawmaker sought to penalize the company for going over budget, announcing a proposal to cut into Southern Co.'s profits by trimming some of the money its subsidiary Georgia Power makes.

And Southern Company and Georgia Power slipped the Plant Vogtle schedule still more, from 15 to 19 months late.

The legislation has a coalition of tea party, conservative and consumer advocacy groups behind it, but faces a tough sale in the Republican-controlled General Assembly. GOP Rep. Jeff Chapman found just a single co-sponsor, Democratic Rep. Karla Drenner.

That's HB 267: Financing costs; construction of nuclear generating plant. And AP failed to mention Georgia Sierra Club's support for HB 267.

As a regulated monopoly, Georgia Power currently earns about 11 percent in profits when it invests its own money into power projects. Chapman's legislation would reduce those profits if the nuclear project is over budget, as is the current projection.

In Florida, there's a move to completely eliminate Construction Work in Progress (CWIP) such as is being used in Georgia to pre-fund the new Plant Vogtle nukes.

In Florida, lawmakers want to end the practice of utilities collecting fees from customers before any electricity is produced.

Florida only recently got CWIP, but Progress Energy has been quick to profit by it:

Continue reading

HB 267 Would Limit Georgia Power’s Profits on Vogtle’s Cost Overruns —GA Sierra Club

There’s still time to contact your state legislators about stopping Georgia Power profitting from cost overruns on the new nukes at Plant Vogtle. Georgia Sierra Club spells out why.

Georgia Power’s expansion at Plant Vogtle will bring us power that is dangerous, expensive and unnecessary.

You may remember a controversial bill the Georgia Legislature approved in 2009, SB 31, the Nuclear Construction Work in Progress (CWIP) bill, which forces Georgia Power ratepayers to pay the financing costs during construction, rather than over the life of the plant. Large users of electricity are exempt from the charge, but residential and mom and pop businesses have been paying for two years.

Even after that sweetheart deal, the Public Service Commissioners scrapped their staff proposal to stop the company from profiting on cost overruns for the project after they top $300 million.

The most recent reports from the independent monitor established by the PSC says

that the project is months behind and as of December, $88 million over budget. Georgia Power gets to earn 11.15% return on all expenses approved by the PSC, so the more they have to spend, the more they get to make and the more ratepayers get to pay!

Putting the profit issue aside for the moment, if the Georgia PSC ever decided to disapprove cost overruns, Georgia Power could take a page from the Mississippi Power playbook and just get the Legislature to let them issue bonds to pay for the work.

HB 267 by freshman Rep. Jeff Chapman excludes the collection of any profits on cost overruns beyond the $6.4 billion the Public Service Commission has approved. The bill is co-sponsored by Avondale Estates Democrat Karla Drenner, who is a member of the Utilities Committee, to which the bill was assigned. Passage of this bill would provide an incentive for Georgia Power to keep expenses down at Vogtle, something that SB 31 failed to do.

It isn’t fair for Georgia Power to profit to the tune of over 11% on delays, overruns and mismanagement, so ask your State Representative to support HB 267.

-jsq

Want to finance solar? Call GA Sen. Jack Murphy today about SB 51

A Georgia Senate committee needs to take it up a bill that would greatly ease financing solar power for your housetop or business roof. Sen. Jack Murphy is the chair, and you can contact him today.

GA SB 51, The Georgia Cogeneration and Distributed Generation Act, was read to the Senate 16 January 2013 and referred to the Committee on Regulated Industries and Utilities. Here’s contact information for the Chair of that Committee:

Continue reading

GA SB 51, The Georgia Cogeneration and Distributed Generation Act

Georgia Senator Buddy Carter has introduced a Senate bill for the current session of the legislature, SB 51, “The Georgia Cogeneration and Distributed Generation Act of 2001”. It attempts to fix Georgia’s special solar financing problem, the antique 1973 Territorial Electric Service Act.

Why 2001? Apparently Buddy Carter has been introducing it every year since then. Last year Georgia Power’s disinformation campaign nuked it when it was SB 401. Has the legislature gotten tired of Georgia Power and its parent the Southern Company being way late and overbudget on those new nukes? Does the legislature want Georgia citizens to get the savings and job benefits of the fastest growing energy source in the country? Will GaSU help with SB 51, or only with GaSU’s attempt to become a solar monopoly utility? You can contact your legislators and tell them what you think. Every one of them who voted for Georgia Power’s stealth-tax rate hike for that nuke boondoggle should vote for SB 51 to start getting Georgia on a clean path to jobs and energy independence.