Tag Archives: cost overruns

Mississippi PSC required spending docs for Kemper Coal: what about Plant Vogtle?

Maybe Georgia PSC could do about Georgia Power’s nuclear Plant Vogtle what Mississippi PSC did about Mississippi Power’s Kemper Coal: hold their parent Southern Company accountable for cost overruns. And for pipelines!

Sam R. Hall blogged for Daily Ledes 1 November 2013, Sources: U.S. Energy Secretary Ernest Moniz to visit Kemper coal plant,

The PSC voted unanimously to require Mississippi Power to provide additional documents justifying their spending on the Kemper plant. The hearing is set for May 2014, when the plant was originally supposed to go online.

“If the PSC rejects some of the spending as imprudent, it could add to the $1 billion in costs that shareholders have already agreed to absorb,” the Associated Press reported last month.

Meanwhile, GA PSC Continue reading

GA PSC abdicates cost oversight for new nukes at Plant Vogtle

Finish it and then send we the taxpayers and ratepayers a bill? What kind of deal is that? So Southern Company already dodged a Fitch downgrade by delaying a decision, and now GA PSC wants to put it off for years more. That also delays solar deployment in Georgia, putting us still farther behind.

Ray Henry wrote for AP yesterday, Ga. approves deal on nuclear plant costs,

A debate over the rising cost of building a nuclear power plant in Georgia will be delayed for years under an agreement approved Tuesday by Georgia’s utility regulators.

The elected members of Georgia’s Public Service Commission unanimously approved a deal that will put off a decision on whether Georgia Power can raise its budget for building two more nuclear reactors at Plant Vogtle (VOH’-gohl) until the first of those reactors is finished. An independent state monitor has estimated the first reactor will be finished in January 2018 at the earliest.

Regulators will continue monitoring company spending but will not make a decision on raising the bottom line budget figure.

So GA PSC will keep watching costs run over budget but will do nothing about it.

Oh, wait, it’s actually worse: Continue reading

Climate change adversely affecting U.S. power grid

Yes, and moving away from baseload coal, nukes, and natural gas and towards distributed solar and wind power will help with that, both directly by making the grid more resilient, and indirectly by slowing climate change.

Clare Foran wrote for NationalJournal 12 August 2013, Climate Change Is Threatening the Power Grid: So says the White House, in a new report that recommends strengthening the grid.

Just days away from the 10-year anniversary of the worst power outage in U.S. history, the White House and the Energy Department released a report on Monday evaluating the resiliency of the nation’s electric grid and recommending steps to prevent future blackouts.

The report called storms and severe weather “the leading cause of power outages in the United States,” and warned against the steep cost of weather-related damage to the electric grid. It put the price tag for electrical failures caused by inclement weather at between $18 billion and $33 billion annually, and noted that costs have increased in recent years, jumping from a range of $14 billion to $26 billion in 2003 to $27 billion to $52 billion in 2012. Storms exceeding a billion dollars in damages (electrical and otherwise) have also become more frequent in the past decade, as the chart below shows.

Well, Entergy’s Arkansas Nuclear 1 (ANO1) is still down more than four months after a fatal accident (hey, look at that; Continue reading

GA PSC member ties Plant Vogtle nuke cost overruns to Kemper Coal in Mississippi

If Georgia Power stonewalls on cost overruns, will it lose at least one Commissioner this time? Long-time nuclear supporter Tim Echols suggested at the hearings this morning that cost overruns at nuclear Plant Vogtle should be capped like Southern Company was forced to do for Kemper Coal by the Mississippi PSC. Standard & Poor’s already downgraded SO because of Kemper Coal and two analysts have downgraded SO for sticking to coal and nukes instead of doing more solar and wind. If SO’s majority part Georgia Power loses the GA PSC, it could be curtains for Plant Vogtle’s new nukes.

Ray Henry wrote for AP this morning, Southern Co. challenged on nuclear plant costs,

Southern Co. subsidiary Georgia Power has asked to raise the budget for its share of massive project by $737 million to roughly $6.85 billion.

Public Service Commission Tim Echols asked whether the firm has considered offering a deal like one it reached in Mississippi over a separate plant that also proved expensive to build. The company has absorbed $540 million in losses in Mississippi and could face more.

Remember, Tim Echols has for two years now been Continue reading

Southern Company only building nukes because they’re not paying, we are –Robert F. Kennedy Jr.

Kennedy said he’d be for nukes if they were safe or economical, but they are neither, while solar and wind are both. After calling the pro-nuke movie Pandora’s Promise a hoax, he addressed “safe” by pointing out the movie’s claimed former anti-nuke leaders were never leaders while major nuclear utility executives are indeed now anti-nuke leaders. (For example, I met former TVA Chairman S. David Freeman in DC where he was testifying against nukes.) Then Kennedy tore into Southern Company’s three-legged nuclear boondoggle and pointed out solar and wind are winning even against massive distortions in the economic playing field caused by public service commissions letting regulated utilities make the rest of us pay for their profits on uneconomic nukes.

Andrew Revkin posted on Youtube 19 June 2013, Robert F. Kennedy Jr. & Director of Pandora’s Promise Spar Over Nuclear Power,

The last nuclear power plant constructed in the world was in Finland. It cost about $11 billion a gigawatt. Now I’m involved with construction right now of one of the largest power plants that’s in north America which is in the Mojave Desert, and it’s a solar thermal plant, and it’s costing about $3 billion a gigawatt….

There’s no individual and there’s no merchant utility that will build a nuclear power plant, because they’re so expensive. You can’t make money on it. The only ones who will build them are regulated utilities like the Southern Company in Georgia… because they make money by spending money. They get reimbursed for their capital costs plus 12 or 15% per year. So they’ll construct it once they get approval from the public utility commission. Then they want to spend as much money on their capital costs because they’re not paying for it. You and I are paying for it.

I don’t think Bill Gates, or I saw Paul Allen was one of the funders of this film, that they’re going to spend their own money building one of these [nuclear] plants….

You could make energy by burning prime rib, but why would you take the most expensive way to do it.

And by last fall, the cost per gigawatt of solar photovoltaic (PV) panels was already under $3 billion per gigawatt so distributed solar PV makes just as much sense as massive desert thermal solar, and both make far more economic sense than nuclear. Plus costs of solar PV keep going down, pushing solar deployments up like compound interest, while nukes always take years to build and always cost more than budgeted. Southern Company is the king of nuke cost overruns, going 26 times overbudget per unit on Vogtle 1 and 2 and already 19 months late and about a billion dollarsoverbudget on Vogtle 3 and 4. Then there are the safety issues: a failed nuke can be Chernobyl or Fukushima and many nukes leak radioactive tritium into groundwater and vent radiation into the air, while a failed solar plant is a bunch of glass.

Robert F. Kennedy Jr wants a level playing field for solar and wind I got into the [solar] industry to show that there was an alternative and that the alternative was economically viable. And not only that, on a level playing field, if we weren’t giving them the subsidies to the incumbents, our technologies would beat them and soundly. They simply couldn’t compete.

He called the movie’s claims that solar and wind don’t work one of the movie’s many big lies because even without a level playing field we already built more solar and wind power in this country last year “than we did all of the incumbents combined”. Plus you’ve got to fuel fossil or nuclear plants, not to mention the toxic waste issues, while once you build solar or wind “it’s free energy forever”. Kennedy also pointed out the electric grid in the U.S. could be rebuilt to deliver solar and wind power as needed for less than has already been spent on breeder reactors that are no longer in use. The filmmaker made no attempt to rebut any of Kennedy’s points about existing solar and wind technologies that already beat nukes, coal, and natural gas, instead going on about pie-in-the-sky modular reactors.

This all illustrates why the Georgia Public Service Commission needs to stop letting Georgia Power and Southern Company suck radioactive profits at the public teat and make them get on with replacing coal with solar instead of letting old coal plant sites sit unused for more than a decade. Oh, and GA PSC needs to halt the Plant Vogtle nuke boondoggle, which is even worse than Southern Company’s Kemper Coal plant in Mississippi as a huge transfer of wealth from the people of the state to a monopoly.

GA PSC: Doug Everrett (1: south Georgia), Tim Echols (2: east Georgia), Chairman Chuck Eaton (3: metro Atlanta), Stan Wise (5 north Georgia), Bubba McDonald (4: west Georgia)

A monopoly that is supposed to be regulated as a public service. By the Public Service Commission whose Commissioners accept massive campaign contributions from employees and law firms of the utilities they regulate. It’s time for GA PSC to bat away the haze of coal smoke and the radioactive taint that surrounds them and go to bat against corruption and for the people of Georgia.

-jsq

What Georgia Power is afraid of: GaSU and Dr. Smith; and you

So what is Georgia Power afraid of that made their CEO Paul Bowers double down on old-style baseload? Competition, that’s what! What could be more scary in the power-monopoly state of the 1973 Territorial Electric Service Act?

GaSU sun On one side, Georgia Power faces GaSU and its 80 or 90 MW solar plant proposal. Walter C. Jones wrote for OnlineAthens 24 September 2012, Proposed solar company could stir up Georgia’s utility structure,

A proposal from a start-up business promises to lower electricity rates by rebating profits to customers if given a chance to compete as Georgia Power Co.’s “mirror image.”

GaSU fb profile image To proceed with its long-range plan of developing 2 gigawatts of solar power, the start-up, Georgia Solar Utilities Inc., wants to start by building an 80-megawatt “solar farm” near Milledgeville as soon as it gets a green light from the Georgia Public Service Commission. GaSU filed its request last week, and as of Monday, it’s still too fresh for public evaluation.

So radical is the proposal that spokespersons for Georgia Power and the Georgia Solar Energy Association said they still were evaluating it and could not comment.

Groups that normally advocate for customers also are staying quiet.

GaSU executives recognize such a big change won’t come easily.

Continue reading

Southern Company’s three-legged nuclear regulatory-capture stool

The failed EDF nuke project at Calvert Cliffs in Maryland makes it clearer why Southern Company (SO) was the first company to get a nuclear permit in 30 years: it was the only one big enough and monopolistic enough to pull it off. Even then it’s such a bet-the-farm risk that even “great, big company” SO only dared to deploy its great big huge scale equipment with the regulatory capture triple-whammy of a stealth tax on Georgia Power bills, PSC approval of cost overruns, and an $8.33 billion federal loan guarantee:

  1. a legislated stealth tax in the form of a rate hike on Georgia Power customers for power they won’t get for years if ever. If you’re a Georgia Power customer, look on your bill for Nuclear Construct Cost Recovery Rider. You’ll find it adds about 5% on top of your Current Service Subtotal. Georgia is one of only a handful of states where such a Construction Work in Progress (CWIP) charge is legal thanks to our regulatory-captured legislature. Doubling down on bad energy bets, Southern Company is also trying to use CWIP to build a coal plant in Mississippi.
  2. A captive Public Service Commission that rubber-stamps costs for Plant Vogtle. In case there was any doubt as to the PSC’s role in legitimizing those new nukes, the very next day Fitch reaffirmed Southern Company’s bond ratings.

    Southern Company’s regulated utility subsidiaries derive predictable cash flows from low-risk utility businesses, enjoy relatively favorable regulatory framework in their service territories, and exhibit limited commodity price risks due to the ability to recover fuel and purchased power through separate cost trackers.

    Translation: Georgia Power customers subsidize SO’s bonds and SO shareholders’ stock dividends. The PSC also approved cost overruns being passed on to Georgia Power customers, and those nukes are already over $400 or $900 million, depending on who you ask. What do you expect when 4 out of 5 Public Service Commissioners apparently took 70% of their campaign contributions from utilities they regulate or their employees or their law firms, and the fifth commissioner took about 20% from such sources? Hm, there’s an election going on right now!
  3. An $8.33 billion federal loan guarantee. Even that’s not good enough for SO and Georgia Power: SO is asking for less down payment.

And what if even one of that three-legged regulatory capture stool’s legs went away? Continue reading