Down, up, down again: Arkansas Nuclear One

Entergy announced August 8th that its Arkansas nuke was back up after a man died there in March, but it only made it to 87% power on August 12th and then back to zero yesterday. There’s no NRC event for yesterday’s downtime: what’s going on? Meanwhile, the dead man’s family is suing Entergy, and Entergy is suing its contractors. Sounds like the Plant Vogtle circular firing squad.

ANO Feb-Aug 2013

THV11 wrote 8 August 2013, Nuclear One unit back on after deadly accident and EBR staff wrote more detail for Energy Business Review 9 August 2013, Entergy restarts Unit 1 at Arkansas Nuclear One power plant,

Prior to restart, the unit needed an extensive restoration, including damage evaluation, repairs to non-nuclear plant components and rescheduling its refueling activities.

The restoration was made compulsory following the collapse of a contractor’s crane on 31 March 2013, while shifting a generator stator out of the turbine building.

Hm, “made compulsory” by whom? NRC? OSHA, which also investigated? Arkansas? Other? Continue reading

Pilgrim nuke down because of cold, heat, leak: when does it ever run?

Down in January, February, April, May, running low March and June, and now likely to go down because of summer heat, under what conditions does Entergy’s Pilgrim nuke near Boston, MA like to run? Entergy also couldn’t keep the power on during the Super Bowl and still has Arkansas Nuclear 1 down since a fatal accident in March. To be fair, many nukes can’t handle heat. Remind me, why are we building more of them?

Pilgrim 1 NRC Power Reactor Status Jan-July 2013

Christine Legere wrote for Cape Cod Times 18 July 2013, Seawater temps too high for Pilgrim cooling,

PLYMOUTH — The ongoing heat wave could force Pilgrim Nuclear Power Station to shut down, as soaring temperatures continue to warm the Cape Cod Bay waters that the plant relies on to cool key safety systems.

Pilgrim’s license from the Nuclear Regulatory Commission requires Continue reading

Arkansas Nuclear 1 still down since fatal accident in March

Apparently we still don’t know why this happened:

At approximately 7:50am on Sunday, March 31, 2013, a 600-ton generator stator fell onto the turbine deck and then about 30 feet to the train bay floor as was being lifted out of the Unit 1 turbine building at the Arkansas Nuclear One plant. One worker was killed and four others injured when the load fell.

Dave Lochbaum wrote for Union of Concerned Scientists 18 June 2013, Fission Stories #139: Arkansas Nuclear One Fatal Event,

The NRC reviewed U.S. nuclear plant experience with lifting loads with cranes between 1968 and 2002. The NRC reported that about two load drops per year happened during this period with ten incidents causing deaths. The NRC’s review concluded that there had been only three very heavy load drops (defined as a load weighing more than 30 tons). ANO-1 makes four.

While accidents can also happen with wind turbines or even installing solar panels on rooftops, a single solar or wind accident doesn’t Continue reading