Remember how Georgia Power customers get to pay for cost overruns on the new nukes? Well, the overruns have already started.
JoAnn Merrigan wrote for WSAV 15 May 2012, Environmental Groups: Plant Vogtle Reactors Almost One Billion Over Budget,
A group of nine national environmental groups says that the two new nuclear reactors being built at Plant Vogtle (near Waynesboro in eastern Georgia) are over budget by up to $1 billion dollars. The opponents say Georgia Power’s share of the cost overruns is currently $400 million and that may cost ratepayers as well as taxpayers who are guranteeing loans in the billions of dollars.
The nine environmental groups, Friends of the Earth, Southern Alliance for Clean Energy, Blue Ridge Environmental Defense League, Center for a Sustainable Coast, Citizens Allied for Safe Energy, Georgia Women’s Action for New Directions, NC WARN, Nuclear Information and Resource Service, and Nuclear Watch South, are also suing:
Continue reading