Cost overruns already starting for Georgia Power’s new nukes

Remember how Georgia Power customers get to pay for cost overruns on the new nukes? Well, the overruns have already started.

JoAnn Merrigan wrote for WSAV 15 May 2012, Environmental Groups: Plant Vogtle Reactors Almost One Billion Over Budget,

A group of nine national environmental groups says that the two new nuclear reactors being built at Plant Vogtle (near Waynesboro in eastern Georgia) are over budget by up to $1 billion dollars. The opponents say Georgia Power’s share of the cost overruns is currently $400 million and that may cost ratepayers as well as taxpayers who are guranteeing loans in the billions of dollars.

The nine environmental groups, Friends of the Earth, Southern Alliance for Clean Energy, Blue Ridge Environmental Defense League, Center for a Sustainable Coast, Citizens Allied for Safe Energy, Georgia Women’s Action for New Directions, NC WARN, Nuclear Information and Resource Service, and Nuclear Watch South, are also suing:

Continue reading

Powering North Carolina with wind, sun, and water

Here's some hard evidence of FERC Chairman Jon Wellinghoff's assertion back in 2009 that baseload is outdated, we don't need any new nukes or coal, because we can get all the new power we need from sun and wind. This study from North Carolina goes further: we don't need coal or nukes at all.

John Blackburn, Ph.D. wrote a report March 2010, Matching Utility Loads with Solar and Wind Power in North Carolina: Dealing with Intermittent Electricity Sources,

Takoma Park, Maryland, and Durham, North Carolina, March 4, 2010: Solar and wind power can supply the vast majority of North Carolina's electricity needs, according to a major report released today. Combined with generation from hydroelectric and other renewable sources, such as landfill gas, only six percent of electricity would have to be purchased from outside the system or produced at conventional plants.

Hourly Power Generation and Load for a sample day in July

"Even though the wind does not blow nor the sun shine all the time, careful management, readily available storage and other renewable sources, can produce nearly all the electricity North Carolinians consume," explained Dr. John Blackburn, the study's author. Dr. Blackburn is Professor Emeritus of Economics and former Chancellor at Duke University.

"Critics of renewable power point out that solar and wind sources are intermittent," Dr. Blackburn continued. "The truth is that solar and wind are complementary in North Carolina. Wind speeds are usually higher at night than in the daytime. They also blow faster in winter than summer. Solar generation, on the other hand, takes place in the daytime. Sunlight is only half as strong in winter as in summertime. Drawing wind power from different areas — the coast, mountains, the sounds or the ocean — reduces variations in generation. Using wind and solar in tandem is even more reliable. Together, they can generate three-fourths of the state's electricity. When hydroelectric and other renewable sources are added, the gap to be filled is surprisingly small. Only six percent of North Carolina's electricity would have to come from conventional power plants or from other systems."

Six percent is a small number. That means most coal plants could be shut down, and no nukes are needed.

Continue reading

FERC and energy demand response

Beyond a smart grid to mix and match the supply solar and wind to get rid of any need for new coal or nuclear plants, as FERC Chairman Jon Wellinghoff recommended three years ago, FERC also has plans to mix and match demand. Energy customers can volunteer to shut off their air conditioners or clothes dryers automatically if there’s not enough supply. This could facilitate adding solar power, by basically acknowledging that it may not always supply a fixed capacity.

Todd Griset wrote for law firm PretiFlaherty 23 April 2012, FERC seeks demand response standards,

Demand response, an innovative strategy to ensuring the integrity of electric grids, is growing in popularity, prompting federal regulators to consider standardizing how demand response performance is measured.

Managing an electric grid entails ensuring a constant balance between electric generation and customer demand for electricity. As customer demand rises, grid operators have traditionally called on more and more generating units. In most markets, grid operators dispatch the lowest-cost units first to keep overall costs down. As a result, generating units needed to meet peak demand tend to be more expensive than baseload generation. Many peaking units also emit more pollutants per unit of energy than baseload units.

In a demand response program, customers can volunteer to be available to reduce their load during times of peak demand. When done right, this reduction in customer demand can play much the same role as dispatching additional generation, but at a lower cost in dollars and environmental impacts. Energy efficiency resources can also play a similar role.

The U.S. Congress and the Federal Energy Regulatory Commission have both recognized that demand response can be a decentralized, crowd-sourced alternative to peaking power plants. Utilities and regional transmission organizations across the nation are implementing demand response programs.

Across the nation…. How about it, Georgia Power, and Georgia EMCs? How are your demand response programs coming?

-jsq

FERC Chairman: baseload outdated; no new nukes needed; go sun and wind

Power companies’ main stated objection to solar or wind is that they are not “capacity” or “baseload” generation because sometimes the sun does not shine and the wind does not blow. And those utilities are required by various state, regional Energy Regulatory Commissions right up to the Federal Energy Regulatory Commission (FERC) to supply capacity or baseload power. That’s their main excuse for coal and nuclear plants. Well, the Chairman of FERC thinks we may not need baseload, nor any new coal nor nuclear plants, either.

Noelle Straub and Peter Behr wrote for ScientificAmerican 22 April 2009, Will the U.S. Ever Need to Build Another Coal or Nuclear Power Plant? The new chairman of the Federal Energy Regulatory Commission doesn’t think so

No new nuclear or coal plants may ever be needed in the United States, the chairman of the Federal Energy Regulatory Commission said today.

“We may not need any, ever,” Jon Wellinghoff told reporters at a U.S. Energy Association forum.

So what will we need?

Continue reading

Ben Hill Coal Plant Cancelled

Ben Hill Coal Plant was cancelled today by Power4Georgians (P4G). Losing Cobb EMC funding plus new air pollution regulations finally had a good effect.

According to SACE PR today, Proposed Ben Hill Coal Plant Cancelled in Georgia: Power4Georgians in Tenuous Position on Plant Washington After Legal Agreement

Clean air advocates and environmental groups won a victory today when Power4Georgians (P4G), the only company trying to develop expensive new coal plants in Georgia, agreed to comply with critical new safeguards against mercury pollution. The company also agreed to cancel the proposed Ben Hill coal-fired power plant and invest $5 million in energy efficiency and renewable projects. The Sierra Club, the Fall Line Alliance for a Clean Environment (FACE), Southern Alliance for Clean Energy (SACE), and the Ogeechee Riverkeeper, represented by GreenLaw and the Southern Environmental Law Center, successfully challenged the permit for Plant Washington issued by the Georgia Environmental Protection Division, and the settlement agreement is pending approval by each group. If built, Power4Georgians’ Plant Washington will have to meet the much more protective emission standards for mercury and other air toxins.

The longterm implications are even better:

Continue reading

Heat Pump —Paul Wolff @ Tybee 2012 02 17

The one on the right is 10 SEER (he had two); the one on the right is a 17 SEER (the new one). The new one has a separate dehumidifier and a two-stage compressor. It doesn’t have to cut on full blast every time, which cut Paul’s energy cost for cooling by 40%.

Here’s the video:


Heat Pump —Paul Wolff, Tybee Island, Chatham County, Georgia, 17 February 2012.
Video by Gretchen Quarterman for Lowndes Area Knowledge Exchange (LAKE).

-jsq

Why and how you can help bring solar power to Georgia

Foot-dragging utilities have stalled SB 401, which would facilitate generating and selling of solar power in Georgia. Here’s why and how you can help fix that.

John Sibley wrote for SaportaReport Sunday, Solar power bill would give Georgians more choices Have you gotten used to thinking you have no choice on your power

Times are changing. More and more of us are discovering choices for managing our power costs. Beyond the time-honored practice of turning off the lights leaving the room, we can find light bulbs that pay for themselves in a year or so; and we can find appliances, water heaters, and air conditioners that pay for themselves in a few years. After that, the savings are like getting part of your power free.

Now, on-site solar power has become an economical option for many. Deals for rooftop solar panels can be done in Georgia today that will provide power for 25 years for as little as 10 cents per kilowatt-hour. Many Georgians can save money from day one. Since rates in Georgia have gone up 49 percent in seven years, they can also protect themselves against increases.

More and more Georgians are choosing on-site solar, but

Continue reading

Programmable electric meter —Paul Wolff 2012 02 17

Paul Wolff showed us his programmable electric meter at his house on Tybee Island.
It shows night, day, evening hours….

That’s exclusive of the solar. This is strictly what I’ve used off the grid. The solar, I keep a spreadsheet.

The still picture shows Paul and Gretchen comparing notes on solar generation and usage over time. He writes his on a pad of paper. She records hers on an iphone. Either way works.

Here’s the video:


Programmable electric meter —Paul Wolff 2012 02 17
renewable energy,
Paul Wolff, The Volta Collaborative (TVC),
Tybee Island, Chatham County, Georgia, 17 February 2012.
Videos by Gretchen Quarterman for LAKE, the Lowndes Area Knowledge Exchange.

-jsq

Weatherstripping —Paul Wolff, Tybee Island, 2012 02 17

Paul Wolff explains weatherstripping on his door on Tybee Island. Inexpensive and very effective.

Here’s the video:


Weatherstripping —Paul Wolff, Tybee Island, 2012 02 17
renewable energy,
Paul Wolff, The Volta Collaborative (TVC),
Tybee Island, Chatham County, Georgia, 17 February 2012.
Videos by Gretchen Quarterman for LAKE, the Lowndes Area Knowledge Exchange.

-jsq

Vermont Comprehensive Energy Plan

Georgia can do this if it wants to, Final Comprehensive Energy Plan 2011
The Comprehensive Energy Plan (CEP) addresses Vermont’s energy future for electricity, thermal energy, transportation, and land use. This document represents the efforts of numerous state agencies and departments, and input from stakeholders and citizens who shared their insights and knowledge on energy issues over the past ten months. The plan can be downloaded from this website or may be viewed at the Department of Public Service, 112 State Street, Montpelier during regular business hours.
More about those public comments:
The release of the Final CEP 2011 includes the CEP Public Involvement Report II (above). This document summarizes the written comments received during the second public comment period, between the release of the CEP Public Review Draft (CEP) on September 13, 2011 and the close of the public comment period on November 4, 2011. Over 1,380 written comments were received via email, the Comprehensive Energy Plan website, and hard copy between July 15 and November 4. Approximately 350 stakeholder groups, including municipal, business, and non-profit entities, submitted comments. Over 830 form-letter comments were signed and submitted by members of at least three different organizations. Over 200 comments were submitted by individual members of the general public.
Real input from the entire state. Imagine that!

Vermont’s population is about 622,000, or the size of a single Congressional district, so maybe it’s easier for them than for Georgia. On the other hand, maybe a regional south Georgia energy policy, or even a county policy, would be possible.

-jsq