Update 2023-07-25: Videos: Probate, Permitting and Inspections Ordinances and fees, Water main extension, Service contracts, court grants, and a fire truck 2023-07-24.
No rezonings, but something much more pervasive at this week’s Lowndes County Commission meetings: Permitting and Inspections Ordinances and a Building Permit Fee Schedule.
Collage, LCC Packet, 2023-07-24
And $10 million in expenditures, mostly on a water main extension.
Cost | What |
---|---|
$9,754,718.88 | Exit 13 Touchton Road Water Main Extension |
$489,310.00 | Motorola SUAII (Evergreen) |
$346,372.00 | Acceptance of FY24 Juvenile Justice Incentive Grant Funding |
$64,205.17 | Fire Rescue Engine 10 Emergency Repair |
$50,000.00 | Approval of FY24 Juvenile Justice Delinquency Prevention Grant Application |
$28,892.56 | Vertiv Service Contract for the Liebert UPS at the 911 Center & the Four Tower Sites |
$10,733,498.61 | Total |
Here is the agenda.www.l-a-k-e.org/govt/loco/2023-07-24–lcc-packet”>on the LAKE website.
The board packet, received in response to a LAKE open records request is on the LAKE website.
LOWNDES COUNTY BOARD OF COMMISSIONERS
PROPOSED AGENDA
WORK SESSION, MONDAY, JULY 24, 2023, 8:30 a.m.
REGULAR SESSION, TUESDAY, JULY 25, 2023, 5:30 p.m.
327 N. Ashley Street – 2nd Floor
- Call to Order
- Invocation
- Pledge of Allegiance to the Flag
- Recognition of Pretrial, Probation, and Parole Supervision Week 2023
- Minutes for Approval
- For Consideration
- Motorola SUAII (Evergreen)
Documents:Motorola SUAll (Evergreen).pdf
- Vertiv Service Contract for the Liebert UPS at the 911 Center & the Four Tower Sites
Documents:Vertiv Service Contract for the Liebert UPS at the 911 Center and the Four Tower Sites.pdf
- Acceptance of FY24 Juvenile Justice Incentive Grant Funding
Documents:Acceptance of FY24 Juvenile Justice Incentive Grant Funding.pdf
- Approval of FY24 Juvenile Justice Delinquency Prevention Grant Application
Documents:Approval of FY24 Juvenile Justice Delinquency Prevention Grant Application.pdf
- Fire Rescue Engine 10 Emergency Repair
- Permitting and Inspections Ordinances
- Building Permit Fee Schedule
Documents:Building Permit Fee Schedule.pdf
- Bid
- Reports – County Manager
- Citizens Wishing to be Heard-Please State Your Name and Address
- Adjournment
-jsq
Investigative reporting costs money, for open records requests, copying, web hosting, gasoline, and cameras, and with sufficient funds we can pay students to do further research. You can donate to LAKE today!
http://www.l-a-k-e.org/blog/donate
Short Link:
Pingback: Videos: Probate, Permitting and Inspections Ordinances and fees, Water main extension, Service contracts, court grants, and a fire truck | On the LAKE front