Missing: CCA Submission of Preliminary Specifications

Has CCA supplied a key document required by the contract? If not, is the contract still valid?

According to “SCHEDULE 1.6.2 DEVELOPMENT SCHEDULE” CCA was supposed to provide to VLCIA

Submission of Preliminary Specifications (Section 1.6.1)
No later than 6 months after receipt of the Survey
CCA did provide a Title Objection Letter 19 November 2010, and that was due “within 30 days of receipt of the Survey”. So these Preliminary Specifications were due about six months ago. Let’s see them!

If those specifications have not been received by VLCIA, maybe the contract with CCA is no longer valid.

Or maybe VLCIA already received the NTP and is moving on with implementing the project. Seems to me the community should be informed, one way or the other.

-jsq